Consolidation of the second floor - Consolidamento del secondo piano

The consolidation of the second floor was a bit more complicated. In order to keep the concrete layer within 10 cm,  L shaped steel bars were laid all around the walls.

Il consolidamento del secondo solaio fu un po' più complicato. Al fine di mantenere lo spessore dello strato di calcestruzzo armato entro i 10 cm, tutt'attorno ai muri perimetrali vennero posizionate delle barre d'acciaio a forma di L.


The L shaped bars were fixed into the walls.
Le barre vennero fissate alle murature perimetrali.









Then it was added the reinforcement metallic net.
Infine venne aggiunta la rete metallica di rinforzo.

1 comment:

Unknown said...

Hello :)

Very nice job (I find this site via an google search for the floor consolidation). And I find the solution with the L attached in the wall via chemical anchors. One question (if it is possible). Can you tell me the dimension of the L (in your case) distance between screws and dimension of the screws?

and this is all that will keep the floor? nothing extra.
and the last question:
how much it is the load of this floor?

thanks
Antoniu